Chernobyl
![]() |
The accident at Chernobyl Unit 4, on 26 April 1986, did not occur during normal operation of the reactor. It happened during a test designed to assess the reactor’s safety margin in a particular set of circumstances. The test, which had to be performed at less than full reactor power, was scheduled to coincide with a routine shut-down of the reactor. |
The Test The test carried out at Chernobyl-4 was designed to demonstrate that a coasting turbine would provide sufficient power to pump coolant through the reactor core while waiting for electricity from the diesel generators. The circulation of coolant was expected to be sufficient to give the reactor an adequate safety margin. A number of reports have been published that have given summaries of the events leading up to the accident. Since the reactor was destroyed, these summaries have been based on interpretation of evidence. They have not been consistent. There are three reasons for this:
The sequence of events which follows has been compiled following a review of a large number of reports and it represents what we consider to be the most likely sequence of events.
|
April 25: Prelude | |
01:06 |
The scheduled shutdown of the reactor started. Gradual lowering of the power level began . |
03:47 |
Lowering of reactor power halted at 1600 MW(t). |
14:00 |
The emergency core cooling system (ECCS) was isolated (part of the test procedure) to prevent it from interrupting the test later. The fact that the ECCS was isolated did not contribute to the accident; however, had it been available it might have reduced the impact slightly. The power was due to be lowered further; however, the controller of the electricity grid in Kiev requested the reactor operator to keep supplying electricity to enable demand to be met. Consequently, the reactor power level was maintained at 1600 MW(t) and the experiment was delayed. Without this delay, the test would have been conducted during `day shift’. |
23:10 |
Power reduction recommenced. |
24:00 |
Shift change.
|
April 26: Preparation for the test | |
00:05 |
Power level had been decreased to 720 MW(t) and continued to be reduced. |
00:28 |
Power level was now 500 MW(t). |
00:32 |
In response, the operator retracted a number of control rods in an attempt to restore the power level. |
01:00 |
The reactor power had risen to 200 MW(t). |
01:03 |
An additional pump was switched into the left hand cooling circuit in order to increase the water flow to the core (part of the test procedure). |
01:07 |
An additional pump was switched into the right hand cooling circuit (part of the test procedure). |
01:15 |
Automatic trip systems to the steam separator were deactivated by the operator to permit continued operation of the reactor. |
01:18 |
Operator increased feed water flow in an attempt to address the problems in the cooling system. |
01:19 |
Some manual control rods withdrawn to increase power and raise the temperature and pressure in the steam separator. |
01:21:40 |
Feed water flow rate reduced to below normal by the operator to stabilise steam separator water level, decreasing heat removal from the core. |
01:22:10 |
Spontaneous generation of steam in the core began. |
01:22:45 |
Indications received by the operator, although abnormal, gave the appearance that the reactor was stable.
|
The Test | |
01:23:04 |
Turbine feed valves closed to start turbine coasting. This was the beginning of the actual test. |
01:23:10 |
Automatic control rods withdrawn from the core. An approximately 10 second withdrawal was the normal response to compensate for a decrease in the reactivity following the closing of the turbine feed valves. |
01:23:21 |
Steam generation increased to a point where, owing to the reactor’s positive void coefficient, a further increase of steam generation would lead to a rapid increase in power. |
01:23:35 |
Steam in the core begins to increase uncontrollably. |
01:23:40 |
The emergency button (AZ-5) was pressed by the operator. Control rods started to enter the core. |
01:23:44 |
Reactor power rose to a peak of about 100 times the design value. |
01:23:45 |
Fuel pellets started to shatter, reacting with the cooling water to produce a pulse of high pressure in the fuel channels. |
01:23:49 |
Fuel channels ruptured. |
01:24 |
Two explosions occurred. One was a steam explosion; the other resulted from the expansion of fuel vapor.
|
The explosions lifted the pile cap, allowing the entry of air. The air reacted with the graphite moderator blocks to form carbon monoxide. This flammable gas ignited and a reactor fire resulted. Results Chernobyl – Main factors in the accident
Chernobyl – Positive Void Coefficient Details
A reactor is said to have a positive void coefficent if excess steam voids lead to increased power generation, and a negative void coefficient if excess steam voids leads to a decrease in power. The coefficient is simply a measure of the speed of change of state of the reactor. When the void coefficient is positive, the power can increase very rapidly because any power increase that occurs leads to increased steam generation, which in turn leads to a further increase in power. Such increases are, therefore, very difficult to control. When the void coefficient is negative, excess steam generation will tend to shut down the reactor. This is, of course, not a safety problem. Most of the world’s operating power reactors have negative void coefficients. In those reactors where same water circuit acts as both moderator and coolant, excess steam generation reduces the slowing of neutrons necessary to sustain the nuclear chain reaction. This leads to a reduction in power. In some reactor designs however, the moderator and coolant are in separate circuits, or are of different materials. In these reactors, excess steam reduces the cooling of the reactor, but as the moderator remains intact the nuclear chain reaction continues. In some of these reactors, most notably the RBMK, the neutron absorbing properties of the cooling water are a significant factor in the operating characteristics. In such cases, the reduction in neutron absorbtion as a result of steam production, and the consequent presence of extra free neutrons, enhances the chain reaction. This leads to excess power production. This excess power production causes additional heating. The additional heat raises the temperature in the cooling circuit and more steam is produced. More steam means less cooling and less neutron absorbtion, and the problem gets worse. All of this can happen very rapidly. If it is not stopped, and it is very difficult to stop because it feeds itself, there will be the sort of event that happened at Chernobyl unit 4. In order to avoid problems with positive void coefficient there are two approaches. Either the reactor characteristics can be altered to reduce the positive void coefficient or systems can be provided that will shut the reactor down very quickly if an increase in power is detected. Since the Chernobyl disaster, the RBMK reactor design has been altered and units have been backfitted to protect them against the effects of the positive void coefficient. |
Immediate Safety Changes
These factors have reduced the positive void coefficient from +4.5Beta [Greek symbol] to +0.7Beta [Greek symbol], eliminating the possibility of power excursion. Beta [Greek symbol] is the delayed neutron fraction, which is neutrons emitted with a measurable time delay. The next consideration was to reduce the time taken to shut the reactor down and eliminate the positive void reactivity. Improvements include:
RBMK Modifications
|
|||||||||||||||
RBMK – Control Rod Redesign One of the post-accident changes to the RBMK was the redesign of the control rods. 179 of 211 control rods are inserted into the core from the top. To improve their effectiveness, they are equipped with “riders” fixed to their bottom end but with a gap between the rider and the bottom tip of the control rod. Approximately 1.0m water columns remained under and above it. When the control rod is in its uppermost position, the rider is in the control rod cooling tube within the fuelled region of the core. The rider being made substantially of graphite, is almost transparent to neutrons, while water, which would occupy the tube otherwise, plays as an absorber. When the reactor is “poisoned” with Xenon and with partially inserted control rods, the major part of the power is produced within the lower region of the core. This means that when the rod started to move down from its uppermost position, the rider removed water from the lower part, causing an increase in reactivity and hence in power. RBMK light-water graphite reactor The Soviet designed RBMK is a pressurised water reactor with individual fuel channels and using ordinary water as its coolant and graphite as its moderator. It is very different from most other power reactor designs as it was intended and used for both plutonium and power production. The combination of graphite moderator and water coolant is found in no other power reactors. The design characteristics of the reactorwere shown, in the Chernobyl accident, to cause instability when low power. This was due primarily to control rod design and a positive void coefficient. A number of significant design changes have now been made to address these problems. |
|||||||||||||||
![]() |
|||||||||||||||
|
|||||||||||||||
![]() |